Clear scope boundaries are the cheapest risk control on a biogas project. Below is the standard battery limit for a power plant and an upgrading plant.

Gas engines

Biogas gensets, 300 kW to 2 MW

Chinese-manufactured gas engines from a proven production line, configured for POME biogas, typically 25–35% below the landed price of a European equivalent for 600–800 kW units.

← 左右滑动查看完整表格 / swipe to see all columns
Model classOutputElectrical efficiencyHeat recoveryVoltage
300 kW300 kW / 375 kVA36–38%≈ 330 kW415 V / 50 Hz
500 kW500 kW / 625 kVA35.2%≈ 560 kW415 V / 50 Hz
600 kW600 kW / 750 kVA35.1%≈ 680 kW415 V / 50 Hz
700 kW700 kW / 875 kVA35.2%≈ 790 kW415 V / 50 Hz
800 kW800 kW / 1,000 kVA≈ 35.2%≈ 900 kW415 V / 50 Hz
1,000 kW1,000 kW / 1,250 kVA35.2%≈ 1,150 kW415 V / 50 Hz
1,500 kW1,500 kW / 1,875 kVA39–41%≈ 1,700 kW415 V / 50 Hz
2,000 kW2,000 kW / 2,500 kVA39–42%≈ 2,300 kW11 kV option

Indicative at full load with 60% CH₄. Final selection based on site gas data. Containerised from 300 kW to 1.5 MW.

Electrical efficiency is taken from the manufacturer gas consumption data below (≈3.50 kWh per Nm³ CH₄), which is lower than the 38–40% sometimes quoted for Chinese units.

Generator end · option

Brushless doubly-fed generator: let the engine follow the gas

POME gas output is not steady. It moves with FFB throughput, pond temperature and rainfall, so a fixed-speed set spends much of the year at 50–70% load — the zone where carbon builds up and the overhaul interval shortens. A brushless doubly-fed generator decouples engine speed from grid frequency: the engine can turn slower when gas is short and faster when it is plentiful, while the terminals stay at 415 V / 50 Hz. The same machine also motors: it can roll the engine up to ignition speed instead of being driven by a separate starter.

01 · No wear parts in the rotor

No brushes, no slip rings

The rotor carries no windings, no slip rings and no carbon brushes. There is nothing to replace on a service interval, no carbon dust in a humid H₂S-bearing atmosphere, and no spark source next to the gas train.

02 · Variable speed

Follows the gas instead of tripping

Speed can swing roughly ±30% while voltage and frequency stay fixed. When gas falls, the set turns slower and holds a healthy load factor instead of dropping into the carbon-building zone, tripping on lean burn or sending gas to the flare.

03 · Part-power converter

Converter sized for slip power only

Only the slip power passes through the converter — typically 25–30% of rating — not the full 100% as with a permanent-magnet set. Smaller converter, lower conversion losses, fewer components carrying full current.

04 · Grid behaviour

Reactive power and soft synchronising

The control winding can supply or absorb reactive power, synchronise with low inrush and ride through voltage dips — useful on weak rural feeders, long 415 V runs and island operation.

Motor ⇄ generator

The same machine can drive, and be driven

A synchronous generator is a one-way device: its rotor is locked to grid frequency, it can only deliver power, and the breaker may only close when voltage, frequency, phase and phase sequence all match. A brushless doubly-fed machine is a motor and a generator in the same frame. Power flows both ways through the control winding: below synchronous speed it draws slip power to generate, above it the slip power is returned to the grid, and when the torque reverses it runs as a motor and drives the engine instead of being driven by it.

Boundary, stated plainly: the converter is sized for slip power, so motoring is a starting, barring and light-drive duty — not continuous full-torque drive. Long motor duty at large slip needs a larger converter; we size it per project and put the number in the quotation.

Four operating states

← 左右滑动查看完整表格 / swipe to see all columns
ConditionStatePower flow
Below synchronous speed, driving torqueMotorGrid → stator; slip power → control winding
Below synchronous speed, braking torqueGenerator, sub-synchronousEngine → stator; slip power taken from the grid
Above synchronous speedGenerator, super-synchronousEngine → stator, slip power returned to the grid
Standing, engine stoppedSynchronous condenserReactive power only

Crossing synchronous speed reverses the slip-power direction. That single change of sign is what makes the machine a motor on one side and a generator on the other — a synchronous machine has no such point because its speed is fixed.

← 左右滑动查看完整表格 / swipe to see all columns
ItemConventional synchronous + AVRPM generator + full-power converterBrushless doubly-fed (BDFG)
Slip rings / brushesCarbon brushes, replaced periodicallyNoneNone
Converter ratingNot applicable (AVR only)100% of generator rating25–30% of generator rating
SpeedFixed by grid frequencyVariableVariable, ≈ ±30%
Motor operationNone — generating onlyYes, full torque via converterYes — starting, barring and light drive
SynchronisingPrecise synchronism requiredSoft, via converterSoft; breaker closes at any speed in range
Part-load behaviourBelow ~70% load, combustion quality and efficiency fallConverter losses apply across the whole rangeEngine stays in its efficient band at lower gas flow
Routine attentionBrush and slip-ring inspection, cleaningBearing and converter coolingBearing and converter cooling
Reactive powerLimited by the AVRVia converter, goodVia control winding, good
Relative capexBaselineHigherBetween the two

Indicative comparison, generator side only. BDFG is quoted as an option on 500 kW–2 MW units once the site gas profile is known. The continuous load range is set by the engine maker, not by the generator; the generator only removes the fixed-speed constraint.

Where it pays: mills where gas output is strongly seasonal, plants that spend months below 70% load, and remote sites where a brush change means a two-day outage and a fly-in technician. On a steady 100% base load with clean, stable gas, a conventional synchronous machine is still the cheaper answer — and we will say so.

Fuel gas

What the engine needs at the inlet flange

All values measured 1 m upstream of the gas pressure regulating valve. Outside these limits the engine is derated and warranty conditions change.

← 左右滑动查看完整表格 / swipe to see all columns
ParameterRequirementWhy
Gas temperature10 – 35 °CCondensation and knock control
Gas pressure3 – 10 kPa(g); ramp ≤ 1 kPa/minStable mixing at the gas train
Dust≤ 5 μm; ≤ 10 mg/Nm³Valve and piston ring wear
H₂S≤ 50 mg/Nm³Acid corrosion of lube oil and liners
Gas humidity≤ 70% RHNo free water in the gas train
CondensateNone at lowest ambient temperatureCold-start and winter operation
NH₃≤ 40 mg/Nm³Formation of ammonium sulphates
Siloxanes≤ 10 mg/Nm³Abrasive silica deposits on valves and plugs
CH₄≥ 45% by volume; ramp ≤ 2%/minStable combustion, no lean-burn trips

Gas consumption

Pure methane demand by rating

← 左右滑动查看完整表格 / swipe to see all columns
RatingCH₄ (Nm³/h)Raw biogas at 45%at 55%at 60%kWh per Nm³ CH₄
500 kW142316 Nm³/h258 Nm³/h237 Nm³/h3.52 kWh
600 kW172382 Nm³/h313 Nm³/h287 Nm³/h3.49 kWh
700 kW200444 Nm³/h364 Nm³/h333 Nm³/h3.50 kWh
1,000 kW286636 Nm³/h520 Nm³/h477 Nm³/h3.50 kWh

Manufacturer data: 142 / 172 / 200 / 286 Nm³ CH₄ per hour for 500 / 600 / 700 / 1,000 kW, i.e. ≈ 0.286 Nm³ CH₄ per kWh. Long-term output on variable biogas runs at 90–100% of rating, so annual energy should be modelled at 90% load.

The parts between the pond and the engine

Balance of plant

Capture

Pond cover & gas collection

HDPE or geomembrane cover, headers, condensate traps, relief and hatches.

Desulfurisation

Biological + iron oxide

Trickling filter for bulk H₂S, polishing vessels in duty/standby.

Conditioning

Chiller, blower, filters

Refrigerated dryer, coalescing filters, Roots blower with VFD, flame arrestor.

Storage

Gas holder

Membrane holder to buffer mill swings and protect the engine.

Safety

Flare & gas detection

Full-flow flare, CH₄/H₂S detection, ESD logic, Ex-rated instruments.

Heat

Heat recovery

Exhaust exchanger and jacket circuit to 85–95 °C hot water, or steam.

Who does what

Scope matrix · biogas plant & upgrading

← 左右滑动查看完整表格 / swipe to see all columns
Work packageKSTS / technology partnerClientNotes
Process design & gas balanceYesData supplyP&ID, GA, mass balance
Pond cover / digesterDesign & supplySite access, earthworksPond survey first
Gas treatment & gas trainYes—Battery limit: engine inlet
Genset & control panelYes—Protection and synchronising
Civil foundationsExecution (CIDB)ApprovalsLocal subcontractors
Electrical reticulationExecutionTransformer / grid415 V; HV by utility
Erection & commissioningYesUtilitiesDOSH witness
O&MOptionSite crewFull contract or advisory
Methane-reforming fuel cell CHP, 7.5 kW to 100 kW

Hydrogen CHP

Bottled 97% biomethane — or raw 60% biogas taken straight from the mill with an integrated purification front end — is reformed to hydrogen on site, then converted by a fuel cell into power and 60–70 °C hot water: no flame, no NOx, no SOx, no particulates. Water is the only by-product. FOB RM 10,000/kW for the bottled-gas version, installation excluded; the raw-biogas version is quoted per site.

← 左右滑动查看完整表格 / swipe to see all columns
ModelFuel input (kW)CH₄ (Nm³/h)Heat recovery (kW)Hot water, 50 K rise (L/h)Indicative price
7.5 kW17.91.807.7132RM 75,000
10 kW23.82.3910.2176RM 100,000
15 kW35.73.5915.4265RM 150,000
20 kW47.64.7920.5353RM 200,000
30 kW71.47.1830.7529RM 300,000
50 kW119.011.9751.2882RM 500,000
75 kW178.617.9776.81,323RM 750,000
100 kW238.123.95102.41,763RM 1,000,000

Basis: methane LHV 9.94 kWh/Nm³; 42% electrical and 43% recoverable heat are manufacturer guaranteed values at rated output (85% overall). Indicative FOB price to a Malaysian port, excluding freight, insurance, SST, installation, civil works, cylinder room, manifold and grid connection: RM 10,000/kW on bottled 97% gas, RM 19,500/kW on raw 60% biogas with integrated purification.

Feed gas

What the reformer needs

← 左右滑动查看完整表格 / swipe to see all columns
ParameterRequirementWhy
CH₄≥ 95% by volumeReforming catalyst needs a concentrated methane feed
H₂S< 1 ppmSulphur poisons the reforming catalyst and the stack
Siloxanes< 0.1 mg/Nm³Silica deposits on catalyst and electrodes
CondensateNoneFree water damages the catalyst bed
SupplyBottled 97% gas at 200 bar via a manifold, or raw biogas at 55–65% through the integrated purification moduleNo pipeline and no on-site hydrogen storage
Raw biogas optionDesulphurisation, CO₂ removal, drying and compression inside the same packageNo separate upgrading plant and no bottled gas needed; investment higher than the bottled-gas version
What the CHP price includes

Supply scope

← 左右滑动查看完整表格 / swipe to see all columns
ItemContent
IncludedReformer, shift reactor, hydrogen purification, fuel cell stack, inverter, heat exchangers, control system, enclosure
OptionalIntegrated front-end purification for raw biogas feed — desulphurisation, CO₂ removal, drying and compression inside the same package, priced per site
ExcludedSST, freight beyond a Malaysian port, civil works, cylinder room and manifold, installation, grid connection, permits
Warranty24 months on the unit; stack 5 years or 25,000 hours, whichever comes first
Delivery4–6 months from order and gas analysis
Price basisBottled-gas version FOB RM 10,000/kW; raw-biogas version with integrated purification FOB RM 19,500/kW. Both installation excluded, valid 90 days, subject to gas analysis and site survey.
Who does what

Scope matrix · hydrogen CHP

← 左右滑动查看完整表格 / swipe to see all columns
Work packageKSTS / technology partnerClientNotes
Sizing & load matchingYesLoad profileSized on the heat and power demand
Fuel chain: upgrading, bottling, manifold — or raw biogas with integrated purificationDesign & supplyCylinder yard / pond gas tapping pointCH₄ ≥ 95% at reformer inlet, H₂S < 1 ppm
CHP unit & control panelYes—Battery limit: gas inlet and AC terminals
Civil foundations & enclosureExecution (CIDB)ApprovalsLocal subcontractors
Electrical & grid connectionExecutionTransformer / utility230/400 V; HV by utility
Erection & commissioningSeparate quotationUtilities & accessNot included in the FOB price
O&MOptionSite crewIncludes stack replacement planning
Permits & SSTAssistApplicant of recordPer Malaysian regulations
Gas-engine heat pump chillers, 30 kW to 480 kW

BHP air-conditioning

There is no electric motor in the drive train. A small gas engine turns an open-drive compressor directly, and the fuel is 97% biomethane from the mill’s own biogas — so the offices, laboratory and worker housing stay cool when the boiler, the turbine and the grid are all down. Engine jacket and exhaust heat is recovered at the same time as 60–90 °C hot water. Technology origin: gas-engine heat pumps were developed and industrialised by the former Sanyo air-conditioning division in Japan; the same class of machine is built in China by Dalian Sino-Tech Precision (Sino-Tech). BHP is that mechanical architecture with the fuel system re-adapted to mill biogas.

← 左右滑动查看完整表格 / swipe to see all columns
ModelCooling (kW)Fuel input (kW)CH₄ (Nm³/h)Heat recovery (kW)Hot water, 50 K rise (L/h)Indicative price
BHP-303030.03.07.5129RM 75,000
BHP-606060.06.015.0258RM 150,000
BHP-120120120.012.130.0517RM 300,000
BHP-240240240.024.160.01,033RM 600,000
BHP-480480480.048.3120.02,067RM 1,200,000

Basis: cooling COP 1.0 on fuel LHV (typical 0.95–1.15; 1 Nm³ CH₄ ≈ 10 kWh of cooling); recoverable jacket + exhaust heat 25% of fuel input; fuel 97% CH₄, H₂S < 10 ppm, 5–20 kPa at the inlet. Indicative equipment price at RM 2,500/kW, excluding installation, civil works, ducts and cooling-water circuit. Units parallel to megawatt scale.

Included

The complete package

Gas engine, open-drive compressor, evaporator and condenser, engine heat recovery, control panel and weatherproof enclosure.

Excluded

Site side

Civil foundation, chilled-water and duct distribution, gas line beyond the inlet flange, installation, SST and permits.

Fuel

Mill biogas, not diesel

Upgraded 97% biomethane from the mill’s own digester gas. No grid connection, no diesel tank, no electric chiller in the critical cooling path.

BHP system page

Biomethane & bio-CNGHydrogen CHPBHP air-conditioningBiogas power plantEquipment & scope

Related sites

Fluid machinery energy-saving calculatorHONGSHI — industrial pumps (export)

KSTS K. S. Technical Services · Sabah, Malaysia

k.s.t.s_sabah@hotmail.com · +60 13-883 3833

© 2026 · Mobile edition

⌂Home ✉Get a study